Liquidated Damages: Enforcement and Reduction

The contract has a liquidated damages clause. When can the injured party recover the full amount without proving loss? What must the party facing the claim show to persuade the court to reduce it?

Liquidated damages fix in advance the monetary liability for a breach of contract. Once the conditions for applying the clause are met, the injured party is entitled to compensation without proving loss. Reducing the amount on the ground that it is excessive is subject to a narrow legal test; asserting that the figure is high is insufficient.

The Breach That Triggers Compensation

Entitlement depends on the agreement’s wording and the breach that occurred. A clause addressing late payment is not the same as one applying to termination or breach of a specific undertaking.

The claimant must establish the obligation that was breached, when the breach occurred and satisfaction of the conditions for compensation. Where the agreement requires notice or an opportunity to remedy the breach, records of compliance form part of the proof of entitlement.

A defense must identify the precise defect in the demand: a breach that has not been proved, an unmet condition, an agreed variation of the obligation or a calculation inconsistent with the agreement.

Reduction Requires Established Legal Grounds

Section 15 of the Contracts (Remedies for Breach of Contract) Law permits reduction of compensation fixed without any reasonable relationship to the loss foreseeable when the agreement was made as a probable consequence of the breach.

The assessment concerns the loss foreseeable in advance from the type of breach that occurred. Lower actual loss, or even no actual loss, does not in itself justify reduction. A reasonable relationship, even a tenuous one, precludes reduction under this test.

The party seeking reduction generally bears the burden of establishing the grounds. However, a blanket clause imposing the same compensation for minor and serious breaches is open to judicial scrutiny by reason of its wording and may shift the burden of proof.

The response to an application for reduction must connect the compensation to the risks foreseeable when the agreement was made. Financing costs, disruption to other transactions and costs arising from delayed performance are examples of data used to substantiate that connection.

Accruing Compensation: The Charging Period Determines the Exposure

For daily or monthly compensation, the duration determines the claim amount. The calculation must identify when liability begins and ends and address extensions, agreed variations and the causes of delay.

Even where the rate for a period is reasonable, accrual over a period extending substantially beyond the foreseeable loss is subject to judicial intervention. In appropriate circumstances, the injured party’s conduct after the breach is also examined in claims for continuing compensation.

The defense must challenge specific periods and components falling outside the obligation. The claimant must justify the full period claimed and credit payments already received.

Selecting Remedies and Preventing Double Recovery

A liquidated damages provision does not in itself exclude a claim for compensation for proven loss instead, or other remedies for the breach.

Selecting the remedy requires comparing the agreed amount with the loss that can be proved. Combining compensation requires showing that the amounts cover distinct losses. There is no entitlement to double recovery for the same loss.

Evidence Supporting the Full Amount Claimed

The agreement and its schedules, notices, performance records, correspondence and payment records must substantiate every component of the demand. A detailed calculation must connect each amount claimed to the contractual provision and the relevant period.

The same evidentiary foundation is needed to address allegations of waiver, an extension, variation of the agreement or partial payment.

Gutman Hertman & Co. represents clients in claims to enforce liquidated damages and in defending demands for payment, in commercial and real estate disputes.